Lyon County Board member Todd Draper responds to an update concerning bids for the Garvin Park improvement project. Because of bids that came in over the estimated budget for the project, the County voted to re-bid and re-advertise it.

LYON COUNTY BOARD MEETING Tuesday, June 6, 2023

Garvin Park bids exceed grant money

Because both bids for the Garvin Park improvement project came in well over the County’s estimated budget and exceeded grant dollars available, the Lyon County Board on June 6 had no other choice but to go back to the drawing board and will re-bid parts of the project.
Lyon County Environmental Administrator Roger Schroeder broke the news to the board in what he called a “somewhat disappointing report” on the project.
“Both bids were over what the grant dollars allowed,” Schroeder told the board. “In talking with the county attorney, we aren’t able to line item vetos on the bid items. There are a few options moving forward.”
The low bid amount for the project came in more than $533,000 over the engineer’s estimate.
“It was about twice as high as the engineer’s estimate,” Schroeder said. “But it also exceeded the amount of grant dollars we have available.”
The County would’ve had to come up with roughly $325,000 to carry on with the project as originally planned. Because of that, the re-bid will remove the bituminous piece and lessen the amount of concrete by roughly 25% in the main picnic shelter area.
“It was a lot of concrete — 10,000-plus square feet of concrete,” said Schroeder. “We were hopeful that it didn’t exceed the grant dollars, but we realize that we kind of made this plan a little bit too big, I suppose.”
The Legacy Grant award — applied for through the Greater Minnesota Parks and Trails Commission — totaled $1,109,350, with a 10% required match from the County ($123,261). Building purchases came out just shy of $437,000.
Schroder said the County had the choice of either honoring the lowest bid, rejecting both bids and re-advertising the project, or remove certain parts on the project, which it ultimately did by taking out the bituminous overlays of the parking lot and work that into the bituminous plan for 2024. Landscaping will also be taken out of the new bid; instead, the County will take on that responsibility, as time allows.
“It will essentially be a new project that we’re bidding,” said Schroeder.
The third option, Schroeder said, would be to put the entire project on pause and consider collecting bids in the fall so work can begin next year. However, that option wouldn’t fit the timeline of the scope of the project.
The news didn’t sit well with commissioners.
“I’ve dealt with bidding for quite a few years, I’ve dealt with engineers — the bottom line is, in my opinion, the engineer dropped the ball — they were using 1980 prices on certain line items,” said Commissioner Todd Draper. “There was a line item that was way under, and that’s why our prices were so much over what we thought. With that being said, Roger has work that needs to be done before the toilets and the shelters come in.”
Key areas in the project that will move forward include replacing all the bathrooms and the main picnic shelter and gathering area, as well another shelter in the main entrance parking lot and the creation of an ADA trail that goes through the woods to the warming house.
Grant dollars will also be used to redo all of the parking lots and build a deck and add landscaping around the warming house.
“Were going to bid that out separately at some time in the future,” Schroder said. “The landscaping and the deck around the warming house was never in this bid.
A motion to reject the bids was made by Draper and seconded by Commissioner Tom Andries. Schroder will now have to put together new specs and re-bid for the project.
The application for the grant was submitted in 2020; the County has until June 30, 2025 to spend the grant monies.
“We have options; I feel good about the time that we have available to go ahead and re-bid,” said Schroeder. “I feel real confident about us being able to kind of repackage everything and put that out there and start advertising by early next week and have bid results back by the first (county board) meeting in July. The timeline is there to allow us to meet the required deadlines.”